Downtown Revitalization Project – Update #20
Downtown Update
Great progress continues on the Meredith Street revitalization! The lockstone installation on the east side is complete, with only finishing touches underway. On the west side, conduit installation has been completed along the south section, and this week crews will continue installing conduits along the remainder of the street.
At the same time, crews will be sanding and applying finishing touches to the east-side lockstone and preparing the west side for curb installation through grading work.
Thank you to everyone for your patience and support as we move closer to a fully renewed downtown!